|
Assume Machine A is a single product machine and is theoretically capable of producing 1,000 units every hour.
In a 16 hour scheduled production day (e.g. 2 x 8 hour shifts) Machine A could theoretically produce 16,000 good units.
On a particular day the equipment/process recorded downtime of 2 hours (e.g. equipement breakdown, waiting on materials etc..)
Scheduled Production Time = 16 Hrs (2 x 8Hr Shift) Downtime (Planned & Unplanned)= 2 Hrs Available Time (Uptime) = 16 Hrs - 2 Hrs = 14 Hrs Available Time / Scheduled Time = 14Hrs/16Hrs = 88% Availability
In this example we will record throughput on the equipment/process as 12,632 units (cycles) for the 14 hrs of Available Time. Also remember that the Machine can produce 1,000 units an hour
Available Time = 14 Hrs Total Product Produced (Throughput) in Available Time = 12,632 units Theoretical time to produce 12,632 units = 12,632/1,000 = 12.63 Hrs Theoretical Time / Available Time = 12.63Hrs / 14Hrs = 90% Performance
Out of the 12,632 units (cycles), it was found that only 12,000 of the units were deemed good units (i.e. shippable units). The other 632 are accounted as scrapped and/or rework cycles to make shippable.
Performance Time = 12.63 Hrs Good Units (expressed in time) = 12,000 units / 1,000 per Hour = 12 Hrs Performance Time / Good Units = 12.63Hrs / 12 Hrs = 95% Quality
Availability x Performance x Quality = 88% x 90% x 95% = 75% OEE
Therefore there are losses totalling 25% for the day (equating to 4 production hours lost).
OEE is about looking at the root causes compiling the 25%, and taking corrective action to reduce the losses and increase the OEE % |